Building Timeline

I naively thought the time from purchase to moving in was going to be 12 months. 4-6 months for all the permitting stuff, 6-8 months for the build. You can see from the timeline below, we are at 8 months and don’t have a building permit yet. Patience is not my strong suit.

June 13, 2019 – Plans being updated with SIP (Structured Insulated Panel) information and energy credits required by Town Planning Dept.

May 29, 2019 – Working on energy credits

April 20, 2019 – Received proposal/quote for HVAC

March 28, 2019 – Design “blessed” by Town Planning

March 15, 2019 – Septic Permit Granted

March 8-ish, 2019 – Engineering completed

February 25, 2019 – Plans finalized, sent to engineering.

January 28, 2019 – Lot cleared

October 12, 2018 – Closed on purchase of lot